23INR0300 · Solar · Midland County
Holzer Solar
Holzer Solar is a 18 MW solar project in Midland County, Texas, connecting at 11165 Sloan Switch 138kV. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 11/16/2026.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 23INR0300
- Capacity
- 18 MW
- Fuel
- Solar (PV)
- Substation
- 11165 Sloan Switch 138kV
- County
- Midland County
- Interconnecting entity
- Greater Bryant G Solar, LLC
- Projected COD
- 11/16/2026
- Entered queue
- 06/16/2021
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 07/02/2026Energization Approved → Sync Approved
- 06/11/2026IA Signed → Energization Approved
- 04/09/2025FIS Requested → FIS Approved
- 07/18/2022FIS Approved → IA Signed
- 06/16/2021Entered the queue with 18 MW, projected COD 11/16/2026
- 06/16/2021Screening → FIS Requested
Other projects at this substation
No other projects at this substation.