23INR0283 · BESS · Carson County
Kota Battery
Kota Battery is a 201 MW battery storage project in Carson County, Texas, connecting at 23900 Alibates 345kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 10/31/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 23INR0283
- Capacity
- 201 MW
- Fuel
- BESS (BA)
- Substation
- 23900 Alibates 345kV
- County
- Carson County
- Interconnecting entity
- Kota Storage, LLC
- Projected COD
- 10/31/2028
- Entered queue
- 06/02/2021
- ERCOT zone
- PANHANDLE
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 06/02/2021Entered the queue with 201 MW, projected COD 10/31/2028
- 06/02/2021Screening → FIS Requested
Other projects at this substation
No other projects at this substation.