23INR0278 · BESS · Andrews County
Tucana BESS
Tucana BESS is a 201 MW battery storage project in Andrews County, Texas, connecting at 1157 Andrews County South 138kV. ERCOT's October 2026 report shows it at the FIS Approved stage with a projected commercial operation date of 03/01/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 23INR0278
- Capacity
- 201 MW
- Fuel
- BESS (BA)
- Substation
- 1157 Andrews County South 138kV
- County
- Andrews County
- Interconnecting entity
- BRP Tucana BESS LLC
- Projected COD
- 03/01/2028
- Entered queue
- 05/10/2021
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 06/18/2025FIS Requested → FIS Approved
- 05/10/2021Entered the queue with 201 MW, projected COD 03/01/2028
- 05/10/2021Screening → FIS Requested
Other projects at this substation
No other projects at this substation.