ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
23INR0261 · Solar · Henderson County

Dodd Solar I

Withdrawn

Dodd Solar I is a 202 MW solar project in Henderson County, Texas, with no point of interconnection listed. It is no longer active in ERCOT's interconnection queue.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
23INR0261
Capacity
202 MW
Fuel
Solar
Substation
Not listed
Interconnecting entity
Not listed
Projected COD
n/a
Entered queue
04/17/2026
ERCOT zone
n/a
Size category
n/a

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 04/17/2026
    Listed as inactive

Other projects at this substation