23INR0180 · Solar · San Patricio County
Jackalope Solar
Jackalope Solar is a 156 MW solar project in San Patricio County, Texas, connecting at 8173 Gibbs 138kV. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 02/05/2026.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 23INR0180
- Capacity
- 156 MW
- Fuel
- Solar (PV)
- Substation
- 8173 Gibbs 138kV
- County
- San Patricio County
- Interconnecting entity
- Peacock Energy Project, LLC
- Projected COD
- 02/05/2026
- Entered queue
- 02/02/2021
- ERCOT zone
- COASTAL
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 09/19/2024Energization Approved → Sync Approved
- 07/30/2024IA Signed → Energization Approved
- 11/18/2021FIS Requested → FIS Approved
- 09/30/2021FIS Approved → IA Signed
- 02/02/2021Entered the queue with 156 MW, projected COD 02/05/2026
- 02/02/2021Screening → FIS Requested
Other projects at this substation
No other projects at this substation.