LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
23INR0104 · BESS · Andrews County

BRP Kamet BESS

COD date passed

BRP Kamet BESS is a 202 MW battery storage project in Andrews County, Texas, connecting at Andrews North – McKenzie Draw Switch 138 kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/01/2025. Its projected COD of 12/01/2025 has already passed without ERCOT approval to synchronize, so the date is likely to move.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
23INR0104
Capacity
202 MW
Fuel
BESS (BA)
Interconnecting entity
BRP Kamet BESS LLC
Projected COD
12/01/2025
Entered queue
09/23/2020
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 09/23/2020
    Entered the queue with 202 MW, projected COD 12/01/2025
  • 09/23/2020
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.