BRP Pyxis BESS
BRP Pyxis BESS is a 207 MW battery storage project in Ward County, Texas, connecting at tap 138kV 1009 Yucca - 11197 Sand Tank Pod. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/01/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 23INR0094
- Capacity
- 207 MW
- Fuel
- BESS (BA)
- County
- Ward County
- Interconnecting entity
- BRP Pyxis BESS LLC
- Projected COD
- 12/01/2028
- Entered queue
- 09/11/2020
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 09/11/2020Entered the queue with 207 MW, projected COD 12/01/2028
- 09/11/2020Screening → FIS Requested