Charger Solar is a 397 MW solar project in Refugio County, Texas, connecting at tap 345kV 8249 Angstrom – 5915 STP. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 09/18/2026.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 23INR0047
- Capacity
- 397 MW
- Fuel
- Solar (PV)
- Substation
- tap 345kV 8249 Angstrom – 5915 STP
- County
- Refugio County
- Interconnecting entity
- AP Solar 4, LLC
- Projected COD
- 09/18/2026
- Entered queue
- 06/07/2020
- ERCOT zone
- COASTAL
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 07/17/2026Energization Approved → Sync Approved
- 06/30/2026IA Signed → Energization Approved
- 09/22/2025FIS Requested → FIS Approved
- 06/05/2021FIS Approved → IA Signed
- 06/07/2020Entered the queue with 397 MW, projected COD 09/18/2026
- 06/07/2020Screening → FIS Requested