ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
23INR0045 · Solar · Van Zandt County

Caney Creek Solar

Caney Creek Solar is a 121 MW solar project in Van Zandt County, Texas, connecting at Tap 138kV 6829 Glen Pine - 6833 Explorer. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 06/21/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
23INR0045
Capacity
121 MW
Fuel
Solar (PV)
Interconnecting entity
HEP Aquamarine Holdings LLC
Projected COD
06/21/2027
Entered queue
09/25/2020
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 12/29/2021
    FIS Requested → IA Signed
  • 02/22/2021
    Screening → FIS Requested
  • 09/25/2020
    Entered the queue with 121 MW, projected COD 06/21/2027

Other projects at this substation

No other projects at this substation.