LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
23INR0029 · Gas · Chambers County

Cedar Bayou 5 (TEF - Due Diligence)

COD delayed 1×

Cedar Bayou 5 (TEF - Due Diligence) is a 697 MW natural gas project in Chambers County, Texas, connecting at 40000 Cedar Bayou 345kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 03/31/2028. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
23INR0029
Capacity
697 MW
Fuel
Gas (GT)
Interconnecting entity
NRG Cedar Bayou 5 LLC
Projected COD
03/31/2028
Entered queue
03/18/2020
ERCOT zone
HOUSTON
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 12/15/2027 → 03/31/2028 (+4 months)
  • 05/30/2025
    FIS Requested → FIS Approved
  • 01/10/2022
    FIS Approved → IA Signed
  • 03/18/2020
    Entered the queue with 697 MW, projected COD 12/15/2027
  • 03/18/2020
    Screening → FIS Requested

Other projects at this substation