23INR0026 · Solar · Lamar County
Baker Branch Solar
Baker Branch Solar is a 469 MW solar project in Lamar County, Texas, connecting at tap 345kV 1692 Paris - 1690 Valley. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 09/30/2026.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 23INR0026
- Capacity
- 469 MW
- Fuel
- Solar (PV)
- Substation
- tap 345kV 1692 Paris - 1690 Valley
- County
- Lamar County
- Interconnecting entity
- Mockingbird Solar Center, LLC
- Projected COD
- 09/30/2026
- Entered queue
- 03/05/2020
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 04/10/2024Energization Approved → Sync Approved
- 04/01/2024IA Signed → Energization Approved
- 10/30/2023FIS Requested → FIS Approved
- 02/14/2022FIS Approved → IA Signed
- 03/05/2020Entered the queue with 469 MW, projected COD 09/30/2026
- 03/05/2020Screening → FIS Requested
Other projects at this substation