22INR0469 · BESS · Cameron County
Harper Energy Storage
Harper Energy Storage is a 82 MW battery storage project in Cameron County, Texas, connecting at Tap 138kV 8314 La Palma - 80229 Villa Cavazos. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 09/15/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 22INR0469
- Capacity
- 82 MW
- Fuel
- BESS (BA)
- County
- Cameron County
- Interconnecting entity
- VESI 31 LLC
- Projected COD
- 09/15/2028
- Entered queue
- 12/03/2021
- ERCOT zone
- COASTAL
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 01/27/2022Screening → FIS Requested
- 12/03/2021Entered the queue with 82 MW, projected COD 09/15/2028