22INR0462 · Solar · Hale County

Old Aqueduct Solar

Old Aqueduct Solar is a 512 MW solar project in Hale County, Texas, connecting at 23920 Blackwater 345kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 06/01/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
22INR0462
Capacity
512 MW
Fuel
Solar (PV)
Interconnecting entity
Old Aqueduct Solar
Projected COD
06/01/2028
Entered queue
12/03/2020
ERCOT zone
PANHANDLE
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 06/29/2021
    Screening → FIS Requested
  • 12/03/2020
    Entered the queue with 512 MW, projected COD 06/01/2028

Other projects at this substation

Old Aqueduct BattBESS301 MWFIS Requested