LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
22INR0443 · BESS · San Patricio County

Bowstring BESS

Bowstring BESS is a 155 MW battery storage project in San Patricio County, Texas, connecting at 138kV 8961 WHITEPT4A - 8418 RINCON4A. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 09/18/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
22INR0443
Capacity
155 MW
Fuel
BESS (BA)
Interconnecting entity
Longbow Energy Storage, LLC
Projected COD
09/18/2028
Entered queue
11/18/2020
ERCOT zone
COASTAL
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 09/09/2025
    FIS Approved → IA Signed
  • 05/30/2023
    FIS Requested → FIS Approved
  • 03/24/2021
    Screening → FIS Requested
  • 11/18/2020
    Entered the queue with 155 MW, projected COD 09/18/2028

Other projects at this substation

No other projects at this substation.