22INR0427 · BESS · Andrews County
BRP Kabru BESS
BRP Kabru BESS is a 202 MW battery storage project in Andrews County, Texas, connecting at 1159 Andrew North - 11284 Blackbird 138kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/01/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 22INR0427
- Capacity
- 202 MW
- Fuel
- BESS (BA)
- County
- Andrews County
- Interconnecting entity
- BRP Kabru BESS LLC
- Projected COD
- 12/01/2028
- Entered queue
- 09/22/2020
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 09/22/2020Entered the queue with 202 MW, projected COD 12/01/2028
- 09/22/2020Screening → FIS Requested
Other projects at this substation
No other projects at this substation.