22INR0401 · BESS · Cameron County
Eval Storage
Eval Storage is a 252 MW battery storage project in Cameron County, Texas, connecting at 80229 Cavazos 138kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 04/30/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 22INR0401
- Capacity
- 252 MW
- Fuel
- BESS (BA)
- Substation
- 80229 Cavazos 138kV
- County
- Cameron County
- Interconnecting entity
- Hecate Grid East Valley Storage LLC
- Projected COD
- 04/30/2029
- Entered queue
- 10/23/2020
- ERCOT zone
- COASTAL
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 02/03/2022FIS Requested → IA Signed
- 11/03/2020Screening → FIS Requested
- 10/23/2020Entered the queue with 252 MW, projected COD 04/30/2029
Other projects at this substation
No other projects at this substation.