22INR0301 · Wind · Jack County

Fortuna Wind

COD date passed

Fortuna Wind is a 295 MW wind project in Jack County, Texas, connecting at Tap 345kV 1429 Jacksboro - 1730 WKrum. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 07/01/2026. Its projected COD of 07/01/2026 has already passed without ERCOT approval to synchronize, so the date is likely to move.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
22INR0301
Capacity
295 MW
Fuel
Wind (WT)
Interconnecting entity
RWE Renewables Development, LLC
Projected COD
07/01/2026
Entered queue
03/06/2020
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 08/08/2024
    FIS Approved → IA Signed
  • 05/09/2024
    FIS Requested → FIS Approved
  • 11/24/2020
    Screening → FIS Requested
  • 03/06/2020
    Entered the queue with 295 MW, projected COD 07/01/2026

Other projects at this substation