21INR0428 · Solar · Leon County
Pecan Prairie North
Pecan Prairie North is a 324 MW solar project in Leon County, Texas, connecting at CTT Yellow Wolf, bus # 79007. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 05/01/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 21INR0428
- Capacity
- 324 MW
- Fuel
- Solar (PV)
- Substation
- CTT Yellow Wolf, bus # 79007
- County
- Leon County
- Interconnecting entity
- CG Leon County II LLC
- Projected COD
- 05/01/2027
- Entered queue
- 09/11/2019
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 03/13/2026FIS Requested → FIS Approved
- 02/26/2021FIS Approved → IA Signed
- 09/11/2019Entered the queue with 324 MW, projected COD 05/01/2027
- 09/11/2019Screening → FIS Requested
Other projects at this substation
| Pecan Prairie South | Solar | 133 MW | IA Signed |