21INR0294 · Solar · Brown County
Mountaineer Solar
Mountaineer Solar is a 329 MW solar project in Brown County, Texas, connecting at 1444 Brown 345 kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 09/01/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 21INR0294
- Capacity
- 329 MW
- Fuel
- Solar (PV)
- Substation
- 1444 Brown 345 kV
- County
- Brown County
- Interconnecting entity
- Mustang Mountaineer Solar LLC
- Projected COD
- 09/01/2029
- Entered queue
- 04/16/2019
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 12/08/2019Screening → FIS Requested
- 04/16/2019Entered the queue with 329 MW, projected COD 09/01/2029