21INR0221 · Solar · Lamar County
Samson Solar 1
Samson Solar 1 is a 250 MW solar project in Lamar County, Texas, connecting at tap both 345kV 1685 FarmersVl - 1695 Moses ckts. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 12/31/2026.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 21INR0221
- Capacity
- 250 MW
- Fuel
- Solar (PV)
- County
- Lamar County
- Interconnecting entity
- Samson Solar Energy LLC
- Projected COD
- 12/31/2026
- Entered queue
- 11/20/2018
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 08/31/2021Energization Approved → Sync Approved
- 06/30/2021IA Signed → Energization Approved
- 08/26/2020FIS Approved → IA Signed
- 06/09/2020FIS Requested → FIS Approved
- 05/03/2019Screening → FIS Requested
- 11/20/2018Entered the queue with 250 MW, projected COD 12/31/2026
Other projects at this substation
| Samson Solar 3 | Solar | 250 MW | Sync Approved |
| Delilah Solar 1 | Solar | 300 MW | Sync Approved |