ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
20INR0236 · Solar · Jackson County

New Hickory Solar

New Hickory Solar is a 209 MW solar project in Jackson County, Texas, connecting at OLD_HCKRY_5 bus 5323 345 kV. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 12/29/2026.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
20INR0236
Capacity
209 MW
Fuel
Solar (PV)
Interconnecting entity
New Hickory Solar LLC
Projected COD
12/29/2026
Entered queue
01/25/2019
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 09/15/2026
    Energization Approved → Sync Approved
  • 07/20/2026
    IA Signed → Energization Approved
  • 06/30/2024
    FIS Requested → FIS Approved
  • 06/30/2020
    FIS Approved → IA Signed
  • 08/12/2019
    Screening → FIS Requested
  • 01/25/2019
    Entered the queue with 209 MW, projected COD 12/29/2026

Other projects at this substation

No other projects at this substation.