20INR0203 · Solar · Hopkins County
Pine Forest Solar
COD delayed 1×
Pine Forest Solar is a 302 MW solar project in Hopkins County, Texas, connecting at Monticello Switch – Allen Switch 345 kV Line. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 02/01/2027. Its projected COD has been pushed back 1 time in the reports compared.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 20INR0203
- Capacity
- 302 MW
- Fuel
- Solar (PV)
- County
- Hopkins County
- Interconnecting entity
- Pine Forest Solar I, LLC
- Projected COD
- 02/01/2027
- Entered queue
- 10/04/2018
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Projected COD moved 10/01/2026 → 02/01/2027 (+4 months)
- 07/03/2025Energization Approved → Sync Approved
- 06/03/2025IA Signed → Energization Approved
- 12/18/2024Screening → FIS Approved
- 07/29/2020FIS Approved → IA Signed
- 10/04/2018Entered the queue with 302 MW, projected COD 10/01/2026
Other projects at this substation