20INR0019 · Wind · Young County
Trinity Hills Wind repower
COD delayed 1×
Trinity Hills Wind repower is a -27 MW wind project in Young County, Texas, connecting at 17002 Garvey Rd 345kV. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 12/31/2026. Its projected COD has been pushed back 1 time in the reports compared.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 20INR0019
- Capacity
- -27 MW
- Fuel
- Wind (WT)
- Substation
- 17002 Garvey Rd 345kV
- County
- Young County
- Interconnecting entity
- Trinity Hills Wind Farm LLC
- Projected COD
- 12/31/2026
- Entered queue
- 07/20/2017
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Projected COD moved 08/29/2026 → 12/31/2026 (+4 months)
- 05/22/2020IA Signed → Sync Approved
- 10/17/2018FIS Approved → IA Signed
- 08/02/2018FIS Requested → FIS Approved
- 09/21/2017Screening → FIS Requested
- 07/20/2017Entered the queue with -27 MW, projected COD 08/29/2026
Other projects at this substation