ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
19INR0075 · Solar · Brown County

Horseshoe Bend Solar

Horseshoe Bend Solar is a 301 MW solar project in Brown County, Texas, connecting at 1444 Brown 345kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 02/20/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
19INR0075
Capacity
301 MW
Fuel
Solar (PV)
Interconnecting entity
Clenera
Projected COD
02/20/2028
Entered queue
06/23/2017
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 02/09/2018
    Screening → FIS Requested
  • 06/23/2017
    Entered the queue with 301 MW, projected COD 02/20/2028