16INR0104 · Wind · Crockett County

Big Sampson Wind

Big Sampson Wind is a 265 MW wind project in Crockett County, Texas, connecting at tap 345kV 76015 Cedar Canyon - 7053 Noelke. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 09/01/2026.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
16INR0104
Capacity
265 MW
Fuel
Wind (WT)
Interconnecting entity
Big Sampson Wind Project, LLC
Projected COD
09/01/2026
Entered queue
05/11/2015
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 06/16/2025
    Energization Approved → Sync Approved
  • 06/04/2025
    IA Signed → Energization Approved
  • 10/30/2024
    FIS Requested → FIS Approved
  • 11/08/2019
    FIS Approved → IA Signed
  • 05/11/2015
    Entered the queue with 265 MW, projected COD 09/01/2026
  • 05/11/2015
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.