Reagan County power projects

Reagan County, Texas has 3 active power projects totalling 618 MW in ERCOT's interconnection queue as of the October 2026 report. Wind is the largest share at 310 MW (50%). The largest single project is Slager Lake Wind (310 MW wind). 1 project has signed an interconnection agreement or reached a later stage. 0 projects in the county are listed as withdrawn or cancelled.

Active projects
3
0.6 GW capacity
IA signed or later
1
33% of active projects
Withdrawn or cancelled
0
listed by ERCOT
Changes tracked
0
since Sep 2026

Changes in Reagan County

No changes in the reports compared so far.

All projects

ProjectFuelMWSubstationStageCOD
Slager Lake WindWind310Tap 345kV 59903 Bearkat – 76000 NORTMC5_1Y; Badger 345 kV StationIA Signed07/01/2029
Old Roman Energy CenterBESS20723868 STILES 138 KVFIS Requested07/26/2029
BRP Musca BESSBESS10060361 Santa Rita 138kVFIS Requested12/01/2027

For residents and landowners

What power projects are planned in Reagan County?
ERCOT's October 2026 report lists 3 active projects in Reagan County totalling 618 MW. The table on this page lists each one with its fuel type, size, substation and stage.
Where do these projects connect to the grid?
Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
What does "IA Signed" mean?
The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
When would construction start?
Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
Does a project in the queue mean it will be built?
No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.