Counties / Texas

Motley County power projects

Motley County, Texas has 3 active power projects totalling 852 MW in ERCOT's interconnection queue as of the October 2026 report. Wind is the largest share at 600 MW (70%). The largest single project is Sitges Wind (600 MW wind). 1 project has signed an interconnection agreement or reached a later stage. 1 project in the county is listed as withdrawn or cancelled.

Active projects
3
0.9 GW capacity
IA signed or later
1
33% of active projects
Withdrawn or cancelled
1
listed by ERCOT
Changes tracked
0
since Sep 2026

Changes in Motley County

No changes in the reports compared so far.

All projects

ProjectFuelMWSubstationStageCOD
Sitges WindWind600Tap 345kV 59904 Cottonwood–60500 Edith ClarkeFIS Requested03/31/2030
Buzios SolarSolar252Tap between Cottonwood (#59904) and White River (#23922)Sync Approved07/31/2026
Buzios BESS SLFBESS0Tap 345kV 59904 Cottonwood - 23922 White River Ckt 2FIS Requested07/01/2029
Collier Ranch SolarSolar253Not listedWithdrawnn/a

For residents and landowners

What power projects are planned in Motley County?
ERCOT's October 2026 report lists 3 active projects in Motley County totalling 852 MW. The table on this page lists each one with its fuel type, size, substation and stage.
Where do these projects connect to the grid?
Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
What does "IA Signed" mean?
The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
When would construction start?
Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
Does a project in the queue mean it will be built?
No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.