LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Counties / Texas

Bosque County power projects

Bosque County, Texas has 3 active power projects totalling 383 MW in ERCOT's interconnection queue as of the October 2026 report. Battery storage is the largest share at 208 MW (54%). The largest single project is Woodland Energy Storage (208 MW battery storage). 0 projects have signed an interconnection agreement or reached a later stage. 5 projects in the county are listed as withdrawn or cancelled.

Active projects
3
0.4 GW capacity
IA signed or later
0
0% of active projects
Withdrawn or cancelled
5
listed by ERCOT
Changes tracked
0
since Sep 2026

Changes in Bosque County

No changes in the reports compared so far.

All projects

ProjectFuelMWSubstationStageCOD
Woodland Energy StorageBESS20868040 Kopperl Substation 345kVFIS Requested10/01/2030
Solheim SolarSolar109Meridian (Bus# 315) - Glen Rose (Bus #319) 69 kVFIS Approved11/01/2027
Symank SolarSolar66Tap 69 kV 37470 TNOLSEN - 37520 TNSYCAMOREFIS Requested12/15/2027
Sultan SolarSolar206Not listedWithdrawnn/a
Sultan BESSBESS204Not listedWithdrawnn/a
Rueter SolarSolar200Not listedWithdrawnn/a
Angus StorageBESS63Not listedWithdrawnn/a
Hickerson BESSBESS0Not listedWithdrawnn/a

For residents and landowners

What power projects are planned in Bosque County?
ERCOT's October 2026 report lists 3 active projects in Bosque County totalling 383 MW. The table on this page lists each one with its fuel type, size, substation and stage.
Where do these projects connect to the grid?
Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
What does "IA Signed" mean?
The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
When would construction start?
Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
Does a project in the queue mean it will be built?
No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.